Welcome to our Bath Remodel Project. The Home Owners
want to spruce up the bathroom. We will be installing a new pedestal
sink and a new tub along with new tile and a new commode. Also there
will be some additional drywall and framework being done in the
kitchen, dining room and living room areas.
This is our daily log of events that unfolded, told in pictures.
02/14/2005 We removed the vanity and
set up for the pedestal sink.
02/15/2005 We removed the tub and got ready for new tub.
02/16/2005 We installed the durock/the tile in the tub area and began
to move the kit/dining room doorway.
02/17/2005 We installed Hardi-backer and tile on bath floor & moved
the doorway over in kit/dining room.
02/18/2005 We grouted the walls, floors, sheet rocked, taped and
bedded and installed accessories.
02/21/2005 We set the sink and caulked the baseboard and crown molding
in and mudded walls.
02/22/2005 We sanded, finished coating walls and textured today.
02/23/2005 We installed the trim and finished the project today. |